During final dimensional inspection, bore diameter failures increased during the second production shift. Specification: 25.00 ± 0.10 mm.
Objective
Contain suspect product, identify the most likely process cause, implement corrective action, and define effectiveness checks.
Investigation path
Pareto the defect categories
Review measurement behavior
Develop cause hypotheses
Use 5 Whys to test the leading path
Define CAPA and verification
Pareto analysis
Focus effort on the vital few defect categories.
Finding: Bore diameter accounts for 57% of observed nonconformances, making it the first investigation priority.
SPC review
Twenty sequential bore measurements. Specification limits are 24.90–25.10 mm.
Finding: Measurements trend upward late in the run and exceed the upper specification limit. This is a signal to investigate process inputs—not proof of a root cause by itself.
Fishbone hypothesis map
Potential causes organized using the 6M categories.
MachineTool wearFixture movement
MethodTool-change intervalSetup verification
MeasurementGauge calibrationTechnique variation
MaterialHardness variationLot variation
ManpowerShift handoffTraining
EnvironmentTemperatureCoolant condition
Next: Evidence points toward a time/run-related change, so tool condition and tool-change method become leading hypotheses.
5 Whys
1. Why did parts fail?
Bore diameter exceeded the upper specification limit.
2. Why did diameter increase?
The machining process drifted as the production run progressed.
3. Why did the process drift?
Synthetic inspection evidence is consistent with progressive cutting-tool wear.
4. Why was wear not addressed earlier?
The preventive tool-change interval did not trigger before dimensional drift appeared.
5. Why was the interval ineffective?
The interval was based on a fixed production count without a documented wear-based verification check.
Simulated root cause: An inadequate preventive tool-change standard allowed progressive tool wear to continue until bore diameter exceeded specification.
CAPA plan
ActionTypeOwnerStatus
Segregate and reinspect suspect productionContainmentQualityComplete
Replace cutting tool and verify first-piece dimensionsCorrectionProductionComplete
Revise tool-change interval using wear/measurement evidenceCorrectiveEngineeringOpen
Add scheduled dimensional verification before predicted driftPreventiveQualityOpen
Principle: CAPA should address both the immediate nonconformance and the system condition that allowed recurrence.
Effectiveness verification
Acceptance criteria
Three consecutive production lots within specification
No repeat bore-diameter NCR during verification window
Stable dimensional trend before tool replacement
Revised work instruction followed and documented
30-day review
0 repeat defects
Simulated post-CAPA result. Effectiveness remains subject to the defined monitoring period.
Close only with evidence: implementation alone does not demonstrate CAPA effectiveness.